Kiln upgrade for Jubilee Sawmill

 
    
Kiln upgrade for Jubilee Sawmill

OneFortyOne's Jubilee Sawmill’s second Continuous Drying Kiln (CDK) is now online, completing a $16 million capital investment project at the site in Mount Gambier.

Jubilee Sawmill General Manager, Paul Hartung, says the kilns are working well and have increased site capacity while improving the quality of the timber dried.

“The CDK’s are powered by our own sawdust and wood waste offcuts, and their efficient design is using less energy to process more timber compared to our old batch kilns,” says Mr Hartung.

“With the old batch kiln we put 150m3 of timber in at a time, drying it at up to 160 degrees to achieve a moisture level down to 12%. These high temperatures can stress the timber.

“With the CDK, we load the timber to move through the drying process. With the efficiencies of shared energy and temperature control, the new kilns have a maximum temperature of 130 degrees which is a lot less aggressive on the timber as it dries.”

Two of four older batch kilns will be reconditioned and remain on site to provide added flexibility and backup for when the CDK’s are offline for maintenance.

The upgrade project is part of a greater Jubilee-wide modernisation programme, including sawing equipment upgrades and a robotic pack wrap and strapping machine.

“The upgrades and new equipment on site are creating better and safer working environments for everyone,” says Mr Hartung.

“The team is also getting the opportunity to gain new skills, work with the latest technology, and enjoy a safer and more modern workplace.”

  • 100 years of hard work

    100 years of hard work

    Separated by World War 1, two brothers nonetheless shared the same dream – to start producing lumber after the war. While one was sadly killed in action, the...

  • 11th Great Walk for New Zealand

    11th Great Walk for New Zealand

    Conservation Minister Tama Potaka joined tangata whenua from Ngāi Tahu and local community members last month to celebrate the opening of New Zealand’s eleve...

  • 20,000th forest machine for Ponsse

    20,000th forest machine for Ponsse

    The 20,000th Ponsse forest machine has been completed at Ponsse’s factory in Vieremä, Finland. After the celebration on 11 December, the Ponsse Bear har...

  • 21-day diesel holdings a step forward, says NRC

    21-day diesel holdings a step forward, says NRC

    The Government’s recent announcement to increase onshore fuel holdings to 21 days for diesel is a significant step forward, says the National Road Carriers A...

  • $40k raised for forestry mental health

    $40k raised for forestry mental health

    Rotorua’s recent Fast & Forward Forestry Expo raised some $40,000 to lead a mental health initiative for forestry at its charity auction dinner last month. O...

  • 50-tonne titan

    50-tonne titan

    The mountain men of logging is what first crossed Iron Test writer, Tim Benseman’s mind when the team arrived at NAB Contracting’s steep and "bluff riddled" ...

  • Search Articles

    NZ Logger Magazine
    Read Now